Closed
Milestone Dec 2, 2019–Dec 10, 2019

NEHRP-2020 Data Updates

  • Update data with corrections from design committee
  • Update QC expectations accordingly

Milestone completed as-of tag: 0.12.0

  • Work items 4
  • Merge requests 1
  • Participants 2
  • Labels 1
Loading
Loading
Loading
Loading
100% complete
100%
Start date
Dec 2, 2019
Dec 2
-
Dec 10 2019
Due date
Dec 10, 2019 (Past due)
4
Work items 4 New issue
Open: 0 Closed: 4
1
Merge requests 1
Open: 0 Closed: 0 Merged: 1